Ejemplo cargadoVerMapea causas raíz con contramedidas en una hoja RCCM. Exporta un PDF para revisión o traspaso.
Worksheet header
Worksheet
Problem statement
OTIF dropped below 98% for 2 weeks due to repeated cutoff misses.
Owner
Ops manager (example)
Area / process
Final pack & despatch
Date
28 Apr 2026
Impact / severity
Customer escalations; premium freight risk
RCCM
Worksheet
Root cause → Countermeasure
Row 1
In progressRoot cause
Hot orders bypass standard sequence; cutoff not protected.
Countermeasure
Introduce daily cutoff protection window + visual sequence rules for hot orders.
Owner
Planner + pack lead
Due
Week 1
Row 2
OpenRoot cause
Line 2 changeovers extend beyond planned duration (skills gap).
Countermeasure
Standardise changeover checklist + cross-train 2 backups; audit weekly.
Owner
Production supervisor
Due
Week 2
Row 3
DoneRoot cause
Barcode verifier bypass after changeover.
Countermeasure
Lock bypass behind supervisor signoff + add start-up verification step.
Owner
Quality
Due
30 Apr
Seguimiento de contramedidas hasta el cierre
Esta hoja es una instantánea de sesión única. Kanrix realiza seguimiento de elementos RCCM con responsabilidad, alertas de vencimiento y vinculación de KPI.